"Six Points" construction continues,
affects MiWay, TTC service, starting July 9



Updated — Wednesday, July 11, 9:33 a.m.


SixPointsConstructionMapFINAL.jpg

After more than ten years of planning, consulting, engineering and designing, the City of Toronto has started Phase 2 of a major construction project to redesign, rebuild and simplify the “Six Points” intersection in central Etobicoke — the complex junction where Bloor and Dundas Streets West meet Kipling Avenue.

(The City already completed some early work — Phase 1 — on the project from 2014 until 2016. During Phase 1, crews worked in the former Westwood cinema lands to prepare the site for new infrastructure — sewers, water-mains, other underground utilities and roadways — clearing trees and grading the land.)

During the project, the City intends to:

  • build a new road network and “at-grade” intersection at Dundas, Bloor and Kipling, with Bloor continuing across Kipling;
  • improve pedestrian facilities including wide boulevards, trees, and street furniture;
  • improve pedestrian access to Kipling Station;
  • improve cycling facilities with separate bike lanes on all major streets; and
  • make more land available for parkettes, public art, new development and other amenities.

Six Points after construction.jpg


Starting Monday, July 9, the TTC is detouring southbound buses operating along these routes, as crews rebuild the ramp to St. Albans Road on the east side of Kipling Avenue:

  • 44 Kipling South;
  • 188 Kipling South rocket.

44-188_Interchange.jpg

This phase of construction on St. Albans Road and the TTC detours continue until August 13.


Since Monday, January 8, the TTC has detoured northbound buses operating along these routes, during construction on the east side of Kipling Avenue:

  • 45 Kipling;
  • 45E Kipling express; and
  • 46 Martin Grove.

45_46_interchange_18.gif

This phase of construction on Kipling Avenue and the TTC detours continue until August 13.


During this stage of the project, the City has also:

  • opened some of the new streets in the former Westwood lands south of Dundas Street West and east of Kipling Avenue to vehicular traffic — but just one lane in each direction;
  • opened part of the new roadway for Dundas Street West east of Kipling Avenue to vehicular traffic — but just one lane in each direction;
  • closed the ramp from eastbound Dundas West to southbound Kipling and from southbound Kipling to eastbound Dundas West.

Crews continue:

  • since May, building the new southern portion of Dundas West, west of Kipling, installing street lighting, separate underground sewer, water and hydro utilities. (The work restricts traffic on Dundas West to just one lane in each direction. It continues until December 31.);
  • building the new St. Albans Road to Kipling Avenue, including grading, streetscaping (landscaping, street lighting and underground cables), roads and curbs. (This work continues until September 30.);
  • building temporary and then permanent intersection improvements and traffic signal systems at Kipling and Dundas West. (This work restricts traffic on Kipling to just one lane in each direction. It continues until December 31.);
  • installing temporary asphalt, new water-mains, storm sewers, sanitary sewers, and streetscaping (including landscaping, street lighting and underground utilities) on the south side of Bloor Street West. (This work restricts traffic to just one lane in each direction from the west side of Dunbloor Road to the Canadian Pacific Railway line. It continues until December 31.); and
  • widening Dunbloor Road along the western edge and building various roadway and boulevard improvements. removing shurbs, installing newstreet lighting and repaving. (This work continues until September 30.)

Six-Points-July-9 - 2018.jpg


Friday, March 17, 2017, crews started Stage 1 of Phase 2 — building the new roadway for

  • Dundas Street West between Aukland and Dunbloor Roads.

Since then, MiWay passengers have expected delays on Dundas West when riding buses along these routes:

  • 1 / 1C Dundas;
  • 3 Bloor;
  • 11/ 11A / 11B Westwood;
  • 20 Rathburn;
  • 26 Burnhamthorpe;
  • 35 / 35A Eglinton;
  • 57 Courtneypark;
  • 70 Keaton;
  • 71 Sheridan / Subway;
  • 76 Square One / Subway;
  • 101 / 101A Dundas express;
  • 108 Meadowale Business express; and
  • 109 Meadowvale express.

TTC passengers have expected delays when riding buses along these routes:

  • 30 Lambton;
  • 49 Bloor West;
  • 111 East Mall;
  • 112 West Mall; and
  • 123 Shorncliffe.

MiWay and TTC passengers can expect delays on Dundas and Bloor Streets West, Kipling Avenue, and St. Albans and Aukland Roads near the Six Points until November 30, 2019.

Since 2014, the TTC also has adjusted the service levels of these routes to compensate for delays resulting from project construction:

  • 45 Kipling local;
  • 45E Kipling express; and
  • 46 Martin Grove.

Construction at the Six Points continues until December 31, 2020.


45 Kipling local

Southbound buses operate along their regular route.

(Updated — Wednesday, July 11, 9:33 a.m.) From Monday, January 8 until further notice Monday, August 13, northbound buses start their trips in Kipling Station, as usually, then proceed:

northward along Aukland Road; and then
eastward along Bloor Street West to Kipling Avenue,
resuming their regular route northward along Kipling.

Northbound buses skip their regular stop

  • on the ramp from St. Alban’s Road to Bloor Street East.

Instead, northbound buses pick up passengers at a temporary stop

  • on Aukland Road north of Dundas Street West.
45E Kipling express

Southbound buses operate along their regular route.

(Updated — Wednesday, July 11, 9:33 a.m.) From Monday, January 8 until further notice Monday, August 13, northbound buses start their trips in Kipling Station, as usually, then proceed:

northward along Aukland Road; and then
eastward along Bloor Street West to Kipling Avenue,
resuming their regular route northward along Kipling.

Buses serve all stops.

44 Kipling South

Southbound buses operate along their regular route.

From Monday, July 9 until Monday, August 13, northbound buses operate along their regular route to Kipling Avenue at the ramp to St. Albans Road, then detour:

northward along Kipling to the ramp to westbound Dundas Street West;
westward along Dundas West;
southward along Aukland Road;
eastward along St. Albans Road; and then
southward into Kipling Station bus terminal,
ending their trips.

Northbound buses skip their regular stop

  • on St. Albans Road at the west service road.
188 Kipling South rocket

Southbound buses operate along their regular route.

From Monday, July 9 until Monday, August 13, northbound buses operate along their regular route to Kipling Avenue at the ramp to St. Albans Road, then detour:

northward along Kipling to the ramp to westbound Dundas Street West;
westward along Dundas West;
southward along Aukland Road;
eastward along St. Albans Road; and then
southward into Kipling Station bus terminal,
ending their trips.

46 Martin Grove

Southbound buses operate along their regular route.

(Updated — Wednesday, July 11, 9:33 a.m.) From Monday, January 8 until further notice Monday, August 13, northbound buses start their trips in Kipling Station, as usually, then proceed:

northward along Aukland Road; and then
eastward along Bloor Street West to Kipling Avenue,
resuming their regular route northward along Kipling.

Northbound buses skip their regular stop

  • on the ramp from St. Alban’s Road to Bloor Street East.

Instead, northbound buses pick up passengers at a temporary stop

  • on Aukland Road north of Dundas Street West.

“Six Points” reconstruction project


Phase 2: March 2017 until spring 2020

Generally, phase 2 construction includes:

  • removing the current structures, roads, and facilities;
  • installing underground infrastructure (including water-mains, storm sewers, sanitary sewers, and utilities);
  • streetscaping (including landscaping, street lighting, and furniture)
  • resurfacing the roadway, improving intersections and installing curbs.

Phase 2 construction stages

Stage 1 - Spring 2017 until winter 2018

Stage 1A

  • building the new Dundas Street West alignment between Kipling Avenue and Bloor Street West;
  • building new Roads A and B;
  • building an underground hydro duct bank under Dundas West Between Aukland Road and Jopling Avenue.

Stage 1B

  • closing the Dundas West / Bloor West intersection for 72 hours to remove asphalt and place temporary ramps to Bloor;
  • building along Dundas West, Road A and Road B
  • closing the bus ramp (Kipling Avenue to Street A) and opening temporary connections (Dundas, Road A, Road B)

Stage 1C

  • rebuilding Bloor West, westbound lanes, east of Dunbloor;
  • building the east side of Kipling and the bus ramp, south of Bloor.

Stage 1D

  • rebuilding the westbound lanes of Bloor;
  • building the Kipling / Dundas intersection.

16ECS-TI-01SP (Six Points Master Contract) - STAGE1.jpg


Stage 2 — Spring 2018 until summer 2019

Stage 2A

  • rebuilding the eastbound lanes of Bloor;
  • rebuilding Dunbloor;
  • building the rest of the south side of Dundas and the Kipling / Dundas intersection; and
  • building new Viking Lane.

Stage 2B

  • realigning Bloor between Dundas and Kipling;
  • building Road C;
  • rebuilding the Dundas eastbound and Kipling / Dundas ramps; and
  • building Dundas between Jopling and Kipling Avenues.

16ECS-TI-01SP (Six Points Master Contract) - STAGE2.jpg


Stage 3 — Summer 2019 until spring 2020

Stage 3A

  • widening Kipling northbound lanes; and
  • removing the Dundas / Bloor bridge structures over Kipling.

Stage 3B

  • widening and rebuilding Kipling southbound lanes
  • building Bloor between Kipling and Prennan Avenue

16ECS-TI-01SP (Six Points Master Contract) - STAGE3.jpg